The project scope includes:

 

  • Edge milling 2 ½” depth at gutter line and then tapering out to zero towards the centerline for the length of the roadways.
  • Sections of road experiencing asphalt failures will be deep patched. Deep patch milled areas will be milled an additional 4” and receive 4” of 25 mm Superpave Asphalt Binder Course.
  • Repaving the entire road length to be flush with the existing gutter line.
  • Thermoplastic stop bar striping.
  • Replacing aging and faded street signage.
  • Sodding disturbed areas.